Country | Albania |
Name and address of Project Execution Agency | Operatori I Sistemit të Transmetimit (OST sh.a)
Attention: Mrs Aurora Vasili Rozani (Head of PIU) Bashkia Tirane, Njesia administrative Kashar, YRSHEK, Rruga dytesore Tirane-Durres km 9 Tirana, Shqiperi, Albania |
Project | Construction of Tirana 3 400/110 kV Substation and Associated Works |
Financing Institute | KfW Entwicklungsbank |
BMZ No. | 2011.66.388 |
KfW Procurement No. | 510127 |
Type of Notice | Prequalification Notice |
Prequalification Applications Submission Deadline | 06. September 2023 |
- Operatori I Sistemit të Transmetimit (OST sh.a), will use funds provided by KfW towards financing the implementation of the project
Construction of Tirana 3 400/110 kV Sub-station and Associated Works
The project comprises one (1) lot, as follows:
Design and construction of a new substation and extension/upgrade of connected existing substations, on a turnkey basis. The scope of work shall include the design, manufacturing, delivering, installation, commissioning, and acceptance testing of the equipment to be installed and the entire substation in every respect and suitable for satisfactory operation.
- Operatori I Sistemit të Transmetimit (OST sh.a), hereinafter referred to as “the Employer”, now invites Applications of firms/joint ventures interested to qualify for Design & Construction of Tirana 3 400/110 kV Sub-station and Associated Works.
- Bidding shall be conducted by means of two stage International Competitive procedure as specified in KfW’s “Guidelines for the Procurement of Consulting Services, Works, Goods, Plant and Non-Consulting Services in Financial Cooperation with Partner Countries”, https://www.kfw-entwicklungsbank.de/PDF/Download-Center/PDF-Dokumente-Richtlinien/FZ-Vergaberichtlinien-V-2021-EN.pdf
- The Contract will be based on FIDIC’s Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant, and for Building and Engineering works, Designed by the Contractor (FIDIC Yellow Book).
- The present Prequalification Document relates to:
-
- Construction of Tirana 3 400/110 kV Sub-station and Associated Works.
- And this prequalification processes regards one (1) Contract.
The Works comprise:
-
- New 400/110 kV Tirana 3 substation:
- 400 kV Switchyard
- 110 kV Switchyard
- two (2) 400/110/20 kV 150 MVA power transformers
- MV and LV cabling
- civil works including substation building
- MV switchgear and AC/DC auxiliaries
- SCMS, telecommunication, control and protection, metering Systems
- earthing and lightning protection systems
- small power and lighting systems
- works in existing 110 kV Substations Selita and Farka
- works for SCMS, telecommunication, control and protection and metering systems for enabling the connection of each of these substations with the new Tirana 3 substation.
- New 400/110 kV Tirana 3 substation:
- The Invitation for Bids is expected to be made on September 2023.
- The Prequalification Document will be provided electronically only, free of charge, upon request to the following e-mail addresses:
The email shall be copied to:
The request must be accompanied by a cover letter, duly signed, and stamped, clearly stating the name of the company and the country of domicile.
- The Prequalification Document will be provided electronically only and will be sent to interested firms to the e-mail address indicated in the cover letter of the request. The document will be provided in PDF format.
- Applicants have to furnish, as part of their applications, documentary evidence establishing their qualifications to perform the contract if their bid is accepted.
The Applications for Prequalification shall be provided in hard copy, accompanied by electronic copy, in accordance with the instructions of the Prequalification Document. The Applications shall be delivered to the address mentioned below, on or before 06. September 2023, 11:00 a.m. CET.
- The Original Application and one (1) hardcopy plus one (1) electronic copy shall be submitted to:
-
- Fichtner GmbH & Co. KG
Attention: Mr. Elmar Neubauer
Sarweystrasse 3
70191 Stuttgart, Germany
One (1) additional copy of the Application plus one (1) electronic copy shall be submitted at the following address:
-
- Operatori i Sistemit të Transmetimit (OST sh.a)
Attention: Mrs Aurora Vasili Rozani (Head of PIU)
Bashkia Tirane,
Njesia administrative Kashar, YRSHEK,
Rruga dytesore Tirane-Durres km 9
Tirana, Shqiperi,
Albania
-
- The opening of the Applications shall take place on 06. September 2023, 11:15 a.m. CET, at
Fichtner GmbH & Co. KG
Sarweystrasse 3
70191 Stuttgart, Germany
12.No liability can be accepted for any costs or expenses incurred by the Applicants in connection with the preparation or delivery of their applications.